Construction 1
-
- August 2025

-
- ①Exterior – Side view

-
- ②Exterior – Stern view

-
- ③Cable pulling work

-
- ④Pre-lining inspection started

-
- ⑤Interior wall lining started (cabin area)

-
- ⑥ROV-LARS delivery

-
- ⑦A-Frame crane delivery

-
- ⑧Bow crane delivery

-
- July 2025

-
- ①Bridge raised-floor construction in progress

-
- ②Cable connection inside bridge console

-
- ③Engine control room sound-insulation floor completed

-
- ④Engine control room interior wall installation

-
- ⑤Vibration-damping material applied to engine-room floor for underwater noise reduction

-
- ⑥Unit-bath installation

-
- ⑦Full of cables

-
- ⑧Temporary ducts supplying cool air throughout the vessel

-
- ⑨Heated discussion with the shipowner

-
- June 2025

-
- ① Moored at the Quay

-
- ② Helicopter Deck and Hangar

-
- ③ Elevator Installation Completed

-
- ④ Thermal Insulation Work on LNG Piping

-
- ⑤ Vibration-Damping Steel Plate Installation

-
- ⑥ Shelf Installation

-
- ⑦ Start of Optical Cable Laying

-
- ⑧ Completed Painted Areas

-
- May 2025
-
- ① Bridge Window Installation Completed

-
- ② Thermal Insulation Work in Research Area

-
- ③ Cable Laying Work Inside the Ship

-
- ④ Rail for Mobile Cart Leading to Aft Observation Deck

-
- ⑤ Delivery of Side-Mounted CTD LARS

-
- ⑥ Delivery of Searchlights for Polar Night Operations

-
- ⑦ Relocation by Tugboat

-
- April 2025

-
- ① Moored at the Quay

-
- ② Laying Cables for Multinarrow-Beam Echo Sounder

-
- ③ Power Converter Panel

-
- ④ Rotary Vane Steering Gear

-
- ⑤ Side-Mounted CTD Door

-
- ⑥ View of Dining Room from Galley Serving Window

-
- ⑦ Piping and Ductwork in the Laboratory Area

-
- ⑧ Thermal Insulation Work in Cabins

-
- March 2025

-
- ① Installation of Ice Window

-
- ② Installation of Anchor Chains

-
- ③ Installation of Observation Winch

-
- ④ Final Block Installation (Helicopter Deck)

-
- ⑤Filling the Dock Ahead of the Launch

-
- ⑥ Ready for the Launch Ceremony

-
- ⑦ Moving from the Dock to Quay Berth

-
- ⑧ CTD Moon Pool LARS

-
- February 2025

-
- ①Block Installation Status as of February 27 (Bow Side View)

-
- ②Propulsion Motor Installation

-
- ③Rudder Stock and Rudder Installation

-
- ④Bridge Block Installation

-
- ⑤Power Conversion Equipment Installation

-
- ⑥Deck Machinery Inside Bow Cover

-
- ⑦Radar Mast, Doppler Tower, etc.

-
- ⑧Observation Winch Delivery

-
- January 2025

-
- ①Block Installation Status as of January 31 (Bow Side View)

-
- ②LNG tank installation

-
- ③Propeller shaft installation work

-
- ④Funnel mark

-
- ⑤Multibeam echo sounder

-
- ⑥CTD transfer cart rails

-
- ⑦Thermal insulation installation completed (LNG tank area).

-
- ⑧Bow mooring deck

-
- ⑨Doppler radar mounting base

-
- December 2024

-
- ①Block Installation Status as of December 27 (Bow Side View)

-
- ②Aft observation deck: Crane post and Jib rest installed

-
- ③Lifeboat Davit installed

-
- ④Inside ship: Outfitting of the main generator exhaust pipes

-
- ⑤Air duct for Anti-Rolling Tank approx. 600mm in diameter

-
- ⑥Side CTD LARS mounting rails (Inverted position)

-
- ⑦Painting work is also gradually progressing

-
- ⑧Radar mast in a laid-down position

-
- ⑨Propellers delivered

-
- November 2024

-
- ① LNG Fuel Tank
-
LNG Fuel Tank (foreground) to be installed on Mirai Ⅱ and TCS (Tank Connection Space, background), which houses equipment for supplying LNG fuel to the DFD engine.
Check out our supplementary blog below! ☟(Available in Japanese)
https://www.jamstec.go.jp/parv/j/blog/20241213.html

-
- ② LNG Fuel Tank
-
View from TCS (Tank Connection Space) side
Check out our supplementary blog below! ☟(Available in Japanese)
https://www.jamstec.go.jp/parv/j/blog/20241213.html

-
- ③Block Installation Status as of November 29 (Bow Side View)

-
- ④Block Installation Status as of November 29(Stern Side View)

-
- ⑤Looking up view from the bottom

-
- ⑥Bridge and Whale Watch Room

-
- ⑦Interior construction progressing steadily

-
- ⑧Funnel

-
- ⑨ Installation work of a 4x4.2m moon pool hatch on the ship's bottom

-
- ⑩Low-voltage distribution panel installation

-
- October 2024

-
- ①Block Installation Status as of October 25 (Bow Side View)

-
- ②Block Installation Status as of October 25 (Stern Side View)

-
- ③Retractable Bow Thruster installation

-
- ④Main generator installation

-
- ⑤Completion of four main generator installations

-
- ⑥Engine control room console

-
- ⑦Exhaust pipe construction

-
- September 2024

-
- ①Retractable Stern Thruster Installation

-
- ②1st Block Installation

-
- ③Side Shell Block Installation

-
- ④Completion of High Voltage Switchboard Installation

-
- ⑤Block Installation Status as of September 27 (Bow Side View)

-
- ⑥Block Installation Status as of September 26 (Stern Side View)

-
- ⑦Pre-Installation of Shower Units in Cabin (White Covering)

-
- ⑧Ceiling Pipes and Electrical Circuits Installed

-
- ⑨Deck Deformation Correction Work in Progress

-
- August 2024

-
- ①Ship Bow Block

-
- ②Recess for Anchor Storage

-
- ③Side Shell Block

-
- ④Bridge Block

-
- ⑤Cabin C+D Deck Integration

-
- ⑥Block with Retractable Stern Thruster

-
- ⑦Ladder Installation Area & Ladder Horn

-
- ⑧Funnel (Chimney)

-
- July 2024

-
- Ventilation Duct

-
- Partition Valve

-
- ③ Engine Room Piping Unit

-
- ④Cabin C area

-
- ⑤Cabin C area

-
- ⑥Cabin C area

-
- ⑦ Assembled Moon Pool Compartment Block

-
- ⑧ Engine Room Main Generator Base

-
- ⑨ Stern Tube for Protecting the Propeller Shaft

-
- June 2024

-
- ①Wire supports in stock

-
- ②Tank heating pipe

-
- ③Tunnel bow thruster installation

-
- ④Ship bottom blocks

-
- ⑤Ship bottom blocks

-
- ⑥Bone structural parts in tight spacing

-
- ⑦Complex curved shapes

-
- ⑧Installing external panels

-
- May 2024

-
- ①Various shapes of blocks

-
- ②Various shapes of blocks

-
- ③Piping and wire support installation begins.

-
- ④Various shapes of blocks

-
- ⑤Various shapes of blocks

-
- ⑥Various shapes of blocks

-
- ⑦Various shapes of blocks

-
- ⑧SUS Clad steel plates for stern

-
- April 2024

-
- ①Surface plate receiving curved blocks

-
- ②Trolley for transporting blocks

-
- ③Plate bending work

-
- ④Verifying bending accuracy

-
- ⑤Plates with plate bending