What are the construction details of this large scientific research vessel, D/V Chikyu?
-
Keel-laying ceremony
(Mitsui Engineering and Shipbuilding Co., Ltd, Tamano, Okayama, Japan)
-
Set up the moon pool and engine room.
-
Set up the No.1 azimuth thruster.
-
Hull section almost complete.
-
Assemble the accommodation and laboratory modules on the hull.
-
Naming and Launching ceremony
-
Bridge navigation systems installed.
-
First Sea Trails
(Equipment and systems adjustments and operation checks).
-
Second Sea Trials (Performance test confirmation).
-
Third Sea Trials (DPS test)
-
Moves to Mitsubishi Heavy Industries, Ltd., Nagasaki shipyard for equipment installation.
-
Drill floor winch and deck cranes installed.
-
Derrick installed.
-
Blow-out preventer (BOP) installed.
-
Final pre-completion sea trials.
-
Completion and delivery.